Building service conduits

Activity Unit Labour Material
Time standard
(hour)
Skill Quantity Product
Installing water-pipe, in chase or in duct,
diameter below 2"
lm 0.46
0.46
plumber
labourer
1.03 m galvanized pipe
Installing gas-pipe, out of wall or in chase, 
weld joints, tested, diameter below 2"
lm 0.58
0.58
plumber
labourer
1.04 m
0.5 pcs
(black) gaspipe
(gas)pipe bracket
Installing PVC drainage pipe, in chase
or in duct, diameter below 110 mm
lm 0.59
0.59
plumber
labourer
0.85 m
0.5 pcs
PVC drainage pipe
PVC bent pipe
Installing asbestos cement drain tube, 
with O-ring joints, in chase or in duct,
diameter: 50-100 mm
lm 0.35
0.35
plumber
labourer
0.95 m
0.28 pcs
1.4 pcs
asbestos cement tube
junction/inlet piece
rubber O-ring
Installing internal stormwater drainpipe lm 0.43
0.43
plumber
labourer
1.03 m asbestos or
cast-iron tube
lm = linear meter