| Activity | Unit | Labour | Material | ||
| Time standard
(hour) |
Skill | Quantity | Product | ||
| Installing plastic delineator post | pcs | 0.46 | labourer | 1 pc | delineator post |
| Installing km stone/sign
(tubular post and plate) |
pcs | 1.16 | labourer | 1 pc | post + sign |
| Installing traffic signs
(including/on posts) |
pcs | 1.78 | labourer | 1 pc
0.05 m3 |
traffic sign + post
concretex |
| Installing guard-rail end-piece | pcs | 0.24 | labourer | 1 pc | end-piece (as planned) |
| Installing metal-plate guard-rail
(off 4 m long rail pieces, including rail-posts) |
lm | 2.0 | labourer | 0.25 pcs
1.0 m 0.03 m3 |
rail post
metal-plate rail concretex |
| Installing angle-steel (bar) railings
(pedestrian gaurd-rail on bridge) |
lm | 2.1 | labourer | 0.0065 t
0.0087 t 0.1 m3 |
rail post
rail panel concretex |
| Installing chain railings/barrier | lm | 1.35 | labourer | 1.25 m
0.85 kg 0.1 m3 |
post
chain concretex |
| Placing lamp-post anchor | pcs | 0.63
2.53 |
fitter
labourer |
1.01 pcs | lamp-post anchor |
| Installing (placing) lamp-post | pcs | 4.6
6.9 |
fitter
labourer |
1.01 pcs | lamp-post |
| Building gully structure (water sink)
(off 50x50 cm prefabricated pieces ) |
lm | 1.72 | labourer | 1.02 m | gully pieces
(blocks) |
| Placing gully-hole grill (48x48 cm) | pcs | 0.67
0.67 |
mason
labourer |
1 pc | gully-hole grill |
| Painting traffic-line markings
(by machine/equipment) |
painted
m2 |
0.36 | a team of
4-6 workers |
0.56 kg
0.056 kg 0.26 kg |
paint
thinner (solvent) glass pearl |
| Painting traffic markings
(manually, at junctions) |
painted
m2 |
0.96 | a team of
4-6 workers |
0.74 kg
0.074 kg 0.026 kg |
festék
higitó üveggyöngy |