| Activity | Unit | Layer thickness (cm) | Skill | Material | |||||||||
| 3.0 | 3.5 | 4.0 | 5.0 | 6.0 | 7.0 | 8.0 | 2x2.5 | 2x3.0 | Quantity | Product | |||
| Time standard (hour) | |||||||||||||
| Cleaning asphalt or concrete surface | m2 | 0.16 | labourer | - | - | ||||||||
| Bituminous aggregate levelling course, variable
thicknessx (BA-35, IB-35, AC-12, etc.) |
m3 | 0.37 | spreader | 2.36 t | hot mix | ||||||||
| Improved BA-35 bituminous aggregatex | m2 | - | - | 0.015 | 0.018 | 0.022 | 0.026 | 0.030 | - | - | spreader | 0.0235 t/cm | hot mix |
| BO-20 bond coursex | m2 | - | - | 0.015 | 0.018 | 0.022 | - | - | - | - | spreader | 0.024 t/cm | hot mix |
| AC-12 fine asphalt concretex | m2 | 0.011 | - | 0.015 | - | - | - | - | - | - | spreader | 0.024 t/cm | hot mix |
| AC-20 asphalt concretex | m2 | - | - | 0.015 | 0.019 | 0.023 | - | - | - | - | spreader | 0.0245 t/cm | hot mix |
| Producing mastic asphalt (at asphalt plant) | m2 | 0.075
0.115 |
0.840
0.123 |
0.096
0.144 |
- | - | - | - | 0.12
0.18 |
0.142
0.213 |
spreader
labourer |