| Activity | Unit | Labour | Material | ||||
| Assembly | Dismantle | Skill | Quantity | Product | |||
| Time standard
(hour) |
First built | Rebuilt | |||||
| External high-duty scaffolding,
below 20 m height, above 10 kN/m2 load-bearing capacity |
m3 | 0.45
0.12 |
0.18
0.06 |
carpenter
labourer |
0.058 m3
0.0162 m3 0.0047 m3 |
0.0039 m3
0.0005 m3 0.0003 m3 |
log (bar)
board lumber |
| Access scaffolding,
at high-duty scaffolds |
m2 | 1.05
0.5 |
0.42
0.26 |
carpenter
labourer |
0.17 m3
0.0522 m3 0.0065 m3 |
0.0113 m3
0.0017 m3 0.0002 m3 |
log (bar)
board plank |
| Internal tubular scaffolding,
single storey, below 10 m height |
m2 | 0.73
0.18 |
0.48
0.12 |
carpenter
labourer |
0.058 m3
11.25 m |
0.001 m3
0.1424 m3 |
board
scaffold tube |
| Internal tubular scaffolding,
multi-storey, above 10 m height |
m2 | 0.81
0.22 |
0.52
0.15 |
carpenter
labourer |
0.067 m3
16.2 m |
0,0011 m3
0.205 m |
boardx
scaffold tube |
| Internal scaffolding assembled
off access scaffold pieces (scales), below 10 m height |
m2 | 0.12
0.16 |
0.05
0.12 |
carpenter
labourer |
0.013 m3
2.45 m 0.059 m3 |
0.0008 m3
0.0612 m 0.001 m3 |
lumber
scale (ladder) board |
| External tubular scaffolding, with
scales (ladders), 2 stands/posts, 2 boards, below 20 m height |
m2 | 0.27
0.06 |
0.16
0.04 |
carpenter
labourer |
3.2 m3
0.0135 m3 0.0023 m3 |
0.04 m3
0.0002 m3 0.00023 m3 |
scaffolding tube
board plank |
| External tubular scaffolding, with
scales (ladders), 2 stands/posts, 2 boards, above 20 m height |
m2 | 0.3
0.06 |
0.2
0.04 |
carpenter
labourer |
3.3 m3
0.0135 m3 0.23 m3 |
0.041 m3
0.002 m3 0.0001 m3 |
scaffolding tube
board plank |
| Bracket scaffolding, single | m2 | 2.49
0.45 |
0.74
0.31 |
carpenter
labourer |
0.055 m3
0.118 m3 0.032 m3 |
0.0019 m3
0.002 m3 0.06 m3 |
log (bar)
board plank |
| Assembling safety railing | 10 lm | 0.36
0.15 |
0.09
0.07 |
carpenter
labourer |
0.036 m3
0.063 m3 |
0.002 m3
0.002 m3 |
log (bar)
plank |
| Safety impale (impaling/planking) | m2 | 0.39
0.04 |
0.1
0.03 |
carpenter
labourer |
0.025 m3 | 0.0008 m3 | plank |
| Assembling stand/support for
RC beam shuttering, height range of 6-10 m, below 20 kN/m2 load-bearing capacity |
lm | 2.03
0.59 |
0.81
0.44 |
carpenter
labourer |
0.29 m3
0.079 m3 0.0048 m3 |
0.02 m3
0.0026 m3 0.0002 m3 |
log (bar)
board plank |
| Assembling stand/support for
RC slab/floor shuttering (plain or slab-and-girder floor), below 10 m height, load-bearing capacity range of 5-12 kN/m2 |
m3 | 0.06
0.08 |
0.02
0.05 |
carpenter
labourer |
0.046 m3
0.0041 m3 0.0008 m3 |
0.003 m3
0.0041 m3 0.0001 m3 |
log (bar)
board lumber |
| Preparing working storey
(platform) of/on scaffolding, single (laminate/layer) boarding |
m2 | 0.18
0.08 |
0.06
0.04 |
carpenter
labourer |
0.067 m3 | 0.0011 m3 | board |
| HÜNNEBECK system scaffold | m3 | 0.066
0.29 |
0.06
0.284 |
carpenter
labourer |
12 kg | - | HÜNNEBECK
scaffold |