Formwork (formwork systems)

Activity Unit Labour
Assembly Dismantle Skill
Time standard
(hour)
PERI system formwork (support included)
Slab/floor shuttering m2 0.27
0.3
0.07
0.07
carpenter
labourer
Wall shuttering m2 0.4
0.48
0.1
0.12
carpenter
labourer
Pier/column shuttering (rectangular) m2 0.4
0.6
0.1
0.15
carpenter
labourer
Pier/column shuttering (cylindric) m2 0.5
0.7
0.12
0.18
carpenter
labourer
Beam shuttering m2 0.4
0.45
0.1
0.1
carpenter
labourer
PERI-RINGER system formwork (support included)
Wall shuttering, single sided m2 0.17
0.2
0.06
0.08
carpenter
labourer
Wall shuttering, double sided m2 0.12
0.15
0.04
0.05
carpenter
labourer
Slab/floor shuttering m2 0.18
0.2
0.09
0.1
carpenter
labourer
SZABOLCS system metal formwork (support included)
Wall shuttering, assembled in-situ m2 1.0
1.4
0.2
0.2
carpenter
labourer
Wall shuttering, pre-assembled large panels m2 0.4
0.5
0.1
0.1
carpenter
labourer
DOKA system formwork (support included)
Wall shuttering, double sided m2 0.45
0.45
0.05
0.05
shutt.fitter
SCAN-FORM rsystem formwork (support included)
Wall shuttering, single sided m2 0.5
0.6
0.02
0.03
carpenter
labourer
Wall shuttering, double sided m2 0.7
0.9
0.04
0.06
carpenter
labourer
Assembling supports/stands 
for slab/roof shuttering
lm 0.04
0.05
0.04
0.06
carpenter
labourer
Assembling slab/roof shuttering m2 0.1
0.14
0.1
0.17
carpenter
labourer
LIFT-FORM construction system
Assembling lift jack/post of 1.2 m 
height (assembling off 2 parts each)
pair 1.0
1.0
0.85
0.85
fitter
labourer
Assembling space lattice structure m2 0.95
0.95
0.85
0.85
fitter
labourer
Load transfer to column or to wall m2 0.8
0.8
0.5
0.5
fitter
labourer
Assembling handrail 10 lm 0.65
0.65
0.45
0.45
fitter
labourer
lifting/elevation speed: 1.5 hour/1.2 m
dismantle speed: 1.4 hour/1.2 m
lm = linear meter