Assembly and other masonry works

Activity Unit Labour Material
Time standard
(hour)
Skill Quantity Product
Building brick sewer (channel) or duct,
concrete bottom, clearance 30x50 cm
m 0.49
0.79
mason
labourer
45 pcs
0.045 m3
0.019 m3
0.007 m3
Standard brick
concretex
mortar for renderingx
mortar for floatingx
Building brick cable-duct,
clearance 12x12 cm
m 0.2
0.2
mason
labourer
8 pcs
3.4 pcs
0.002 m3
standard brick
duct block
mortar for masonryx
Building rabitz (mesh) channel (duct)
(gypsum or cement)
m 2.3
2.3
mason
labourer
0.041 m3
1.05 m2
2 kg
0.025 m3
gypsum- or cement-mortar
rib-wire mesh
reinforcing steel
wood plank
Concrete pavement, cast on site,
gravel bedding, not thicker than 8 cm
m2 0.35
0.48
mason
labourer
0.088 m3
0.084 m3
concretex
gravel
Concrete pavement, precast stone flags
(e.g. 40x40 cm)
m2 0.25
0.43
mason
labourer
6.32 pcs stone flag
Concrete gutter (channel),
on 8 cm gravel bed
lm 0.24
0.21
mason
labourer
0.041 m3
0.035 m3
0.01 m3
concretex
gravel
shutter board
Concrete coping, not thicker than 10 cm,
on chimney, on fence- or fender-wall, etc.
m2 0.9
0.45
mason
labourer
0.092 m3
0.024 m3
concretex
shutter board
x See Appendices
lm = linear meter