In-situ plain concrete and RC structures

(preliminary and posteriory works)

Activity Unit Labour Material
Time-standard
(hour)
Skill Quantity Product
Mixing concrete or mortar, 
drum-mixer feeded manually
m3 2.22 labourer x
Mixing concrete, 
drum mixer and power feeder
m3 0.38 labourer x
Mixing mortar, power mixer m3 0.67 labourer x
Processing reinforcing steel 
at central steel plant
(straightening, cutting, bending)
t 9.6
4.8
steel fixer
labourer
1.04 reinforcing steel
Fixing reinforcement on site t 14.2
7.6
steel fixer
labourer
1.04 reinforcing steel
Processing reinforcing steel and 
fixing reinforcement on site
(straightening, cutting, bending, fixing)
t 25.6
12.8
steel fixer
labourer
1.04 reinforcing steel
Fixing weld steel-mesh 
(manufactured) reinforcement
t 12.3
4.1
steel fixer
labourer
1.04 weld settel-mesh
reinforcement
Preparing contraction joint, power saw, 
bitumen joint-sealing
m 0.18 labourer 0.02 t rubberized asphalt
Preparing expansion joint, power saw, 
bitumen joint-sealing
m 0.24 labourer 0.02 t
0.0124 t
0.911 m2
rubberized asphalt
bitumen
120 bitumen felt
x See Appendices