| Activity | Unit | Labour | Material | ||
| Time-standard
(hour) |
Skill | Quantity | Product | ||
| Preparing, adjusting and lowering RC piles | m | 5-6 workers/equipment
3 m/hour |
labourer | 1.015 m | RC pile |
| Bored RC piling | m | 4-5 workers/equipment
0,5 m/hour |
labourer | x
xxx 0.034 m |
concretex
reinforcement guide pipe |
| SOIL-MEC bored piling | m | 6-8 workers/equipment
4 m/hour |
labourer | x
x xxx 1.15 m |
concretex
slurry reinforcement sleeve pipe |
| Franki-system piling | m | 5-6 workers/equipment
2 m/hour |
labourer | 0.45 m3 | concretex |
| Sheet-wall piling
(excavation, slurry, reinforcement, concreting) |
m2 | 12 workers/equipment
20 m2/shift |
labourer | x
xx xxx |
concretex
slurry reinforcement |
| Chiselling-off pile cap or leader beam
air compressor + plugger (air-hammer) |
m3 | 15 hours/plugger | labourer | - | - |