| Activity | Unit | Labour | Material | ||
| Time-standard
(hour) |
Skill | Qunatity | Product | ||
| Blinding, thickness below 10 cm | m3 | 4.43 | labourer | 1.01 m3 | concretex |
| Concreting plain concrete or RC strip foundation,
footings, slab- (mat-) or beam-grid fundation including compacting |
m3 | 3.19 | labourer | 1.01 m3 | concretex |
| Concreting plain concrete or RC strip foundation,
footings, slab- (mat-) or beam-grid fundation applying concrete pump |
m3 | (x) | labourer | 1.01 m3 | concretex |
| Concrete filling in sleeve foundation | m3 | 9.82 | labourer | 1.01 m3 | concretex |
| Gravel fill, spreaded in layers of width 20-50 cm
including compacting, in grade |
m3 | 0.29 | labourer | 1.14 m3 | gravel |
| Gravel bed spreaded in grade,
thinckness range 10-20 cm |
m3 | 0.17 | labourer | 1.14 m3 | gravel |
| Recovering gravel bed | 10m2 | 0.5 | labourer | - | - |